ZEN LUXURY COMPLEX
Construction Progress Update
Date: 10 October 2025
CONSTRUCTION CURRENT REPORT
◉ MAIN OFFICE BUILDING
Completed all concrete works.
Gas block installation on the second floor сurrently underway.
MEP works currently underway in ground and first floors.
◉ APARTMENT BLOCK 1
Concrete works completely finished.
Gas block installation on the ground floor completed.
Ceramic installation on the ground floor сurrently underway.
Already started gypsumboard works.
Gas block installation on the first floor completed.
Ceramic installation on the first floor сurrently underway.
Gas block installation on the second floor сurrently underway.
Ceramic installation on the second floor сurrently underway.
MEP works currently underway in ground and first floors.
◉ BASEMENT – APARTMENT BLOCK 1
Completed pipe installations.
◉ APARTMENT BLOCK 2
Concrete works completely finished.
Gas block installation on the ground floor completed.
Ceramic installation on the ground floor сurrently underway.
Already started gypsumboard works.
Gas block installation on the first floor completed.
Ceramic installation on the first floor сurrently underway.
Gas block installation on the second floor сurrently underway.
Ceramic installation on the second floor сurrently underway.
MEP works currently underway in ground and first floors.
◉ APARTMENT BLOCK 3
Concrete works completed on third floor.
Gas block installation on the ground floor completed.
Ceramic installation on the ground floor сurrently underway.
MEP works currently underway in ground and first floors.
◉ 2 BEDROOM VILLAS
Ground floor completed.
First floor completed.
Rooftop floor completed.
Concrete works сurrently underway on roof.
◉ 3 BEDROOM VILLAS
Borepile works currently underway.
*This project is running active, check this page regularly to get the latest construction updates!