ROOFTOP RESTAURANT
APARTMENT
INFINITY POOL
BASEMENT
CINEMA & YOGA
2 BEDROOM VILLAS
3 BEDROOM VILLAS
ZEN LUXURY COMPLEX
◉ Office Building
– 4th Floor and 3rd Floor slab casting has been completed.
– Overall structure progressing according to schedule.
◉ Apartment Blocks
Block 1
* 3rd Floor slab has been poured.
* Currently ongoing: column works for the 3rd Floor.
Block 2
* 2nd Floor slab was poured yesterday.
* Currently ongoing:
* Column works for the 2nd Floor, and
* Formwork and reinforcement for the 2nd Floor slab.
Block 3
* Basement formwork has been completed.
* Concrete pouring for the basement is scheduled in 2 days.
3. Villas
* Borepile works for all villas are completed.
* Plumbing works are currently in progress.
* Within the next few days, we will:
* Complete plumbing,
* Proceed with backfilling, and then
* Start the foundation works.
Note: The contruction is proceeding according to schedule. Web will keep you updated on the next stages.