UNIT OF THE COMPLEX
ZEN LUXURY COMPLEX
23 February 2026
– AAC block installation ongoing
– Façade works started
– Electrical and mechanical works in progress
– Drywall completed, units ready for wall panels
– Corridor drywall and tiling completed
– Balcony tiling completed
– AAC block installation completed
– Internal tiling nearing completion
– Façade completed, window installation started
– Drywall completed, units prepared for wall panels
– Corridor tiling completed
– Balcony tiling completed
– AAC block installation completed
– Tiling works nearing completion
– Façade works started
– Window installation in progress
– Rooftop steel works underway
– AAC block installation (3rd floor) completed
– Plastering and engineering works ongoing
– Electrical installation completed
– Tiling works started
– Concrete works completed
– Electrical works ongoing
– AAC block installation started
Construction is progressing according to schedule, with reduced risk and increasing readiness as the project moves deeper into finishing stages.